Corporate Transitional Plan

Monthly Progress Report – September 2026

 

Overall Status: Amber
Housing and Environment continue to present delivery challenges, whilst Community, Resilience and Services remain on track. No outputs are currently rated off-track and key transition activities remain progressing towards Vesting Day arrangements. The programme continues to support service continuity whilst preparing the Council for transition to West Surrey Council.


Key Achievements This Period

Key actions are grouped along with KPIs under the specific priorities within the Transitional Plan

Community

Housing

Resilience

Environment

Services

Programme Performance under each priority

Area

On Track

At Risk

Complete

Off Track

Unrated

Community

3

0

3

0

1

Housing

3

6

1

0

0

Resilience

5

0

0

0

0

Environment

2

3

1

0

1

Services

5

0

0

0

0

Total

18

9

5

0

2

Housing accounts for two-thirds of all amber-rated outputs, with the remaining amber items within Environment. No outputs are currently rated red.


Transitional Plan KPIs for main themes within  the Plan

KPI

Measure

Status

Programme Delivery

18 of 27 active outputs on track

🟢

Risk Management

No outputs currently off-track

🟢

Service Transition Readiness

Staff transition, communications and performance reporting activities progressing as planned

🟢

Local Government Reorganisation Preparation

West Surrey transition arrangements and business engagement activities progressing

🟢

Housing Improvement Programme

6 housing outputs remain at risk requiring management attention

🟠

Planning & Environment Programme

Local Plan and Staines Masterplan activities remain at risk

🟠

Completed Deliverables

5 transitional plan outputs completed

🟢

Overall KPI Status: Amber due to the concentration of at-risk activities within the Housing and Environment themes.


Risks and Mitigations

Risk

Mitigation

Continued delays to Housing Action Plan, temporary accommodation reduction and HMO backlog activities.

Regular performance monitoring, targeted resource deployment and escalation through programme governance.

Local Plan evidence base and review timetable could impact strategic planning readiness.

Maintain programme oversight and prioritise completion of key evidence and consultation milestones.

Delays to Staines Masterplan and associated site briefs.

Close monitoring of project milestones and engagement with key stakeholders.

Local Government Reorganisation activity creates competing demands on staff resources.

Ongoing programme management and prioritisation of critical transition activities across service areas.


Next Steps

 

Overall Assessment

The Corporate Transitional Plan remains broadly on track, with strong progress across Community, Resilience and Services. Housing and Environment continue to require focused management attention; however, no activities are currently rated off-track. The programme remains aligned to supporting service continuity and preparing the Council for transition to West Surrey Council.